What’s Going There?

Welcome to our page dedicated to keeping you updated and informed about construction-related projects around Town!

***This page is constantly being updated – have a question about something you don’t see here? Contact Town Hall!

 

Approved/Active Projects:


Horizon Farm Credit

location of horizon farm credit property

Where: 101 Passwaters Farm Road, between S. Main Street and Heritage Shores

What: A 19,880 square foot office building and training center

Links: Plan Sets: May 19, 2026 Planning and Zoning Meeting – https://bridgeville.delaware.gov/events/planning-and-zoning-meeting-38/

Look for the “Rendered Elevation” for concept photos of the building.

Horizon Farm Credit Business Information

 

 


Bridgeville Town Center

Where: Directly behind Food Lion  – 46+ Acres fronting Seashore Highway to the East and Route 13 to the West

btc

What: Mixed-Use Development Consisting of 330 Multi-Family Units, 100 Key Hotel, 99,500 sq. ft. of Retail; Entitlements and Ground-Up Construction

This project was first introduced to the Town of Bridgeville in 2019.  Final approvals were issued in 2024, and construction has officially started.

Links: 

Plan Sets – October 15, 2024 Planning and Zoning Meeting (Approved at the November 12, 2024 Commission Meeting) –  https://bridgeville.delaware.gov/events/planning-and-zoning-meeting-copy/

Developer’s Website (with concept photos) – https://apenninedev.com/bridgeville-town-center/

Original Brochure – (No longer under Mackenzie Commercial) – Bridgeville Town Center Brochure


 

Bridgeville Town Hall – Town Park Project

Where: 103 S Main Street – Between Town Hall and the Police Station

Construction at Town Hall

What: Parking Lot Improvements Project and Town Park

Update: As of Late Summer 2026, we are underway with Phase II of the park project! The Town has been working with playground design companies, using our remaining funding, to create a suitable playground and equipment design for this space. The goal is to have the site designed by winter, with installation in Spring 2027.

We are happily underway with the first phase of our park project! This work is made possible through community redevelopment funds, awarded by Senator Dave Wilson and Representative Jesse Vanderwende. Several elements will exist on this site, and we are just in the beginning. This project has been in planning and progress since 2021, and a concept plan is available on our new website page to help visualize the plan.  We are combining the three entrances to Town Hall and the Police Station due to traffic and safety concerns, reworking the entrance and Town Hall parking lot, adding a designated space for our large holiday tree, creating a new space for a new LED sign/message board, and, of course, creating a small community park space.  Last but certainly not least, this first phase of the project will also create the home of our memorial bricks project.  The memorial bricks project first began in 2019 and was placed on hold during the COVID pandemic.  From there, the bricks were re-incorporated into the new park plan, and we are now finally close to having them installed! Town staff is organizing prior brick reservations. We will be reaching out to all who contributed individually and announcing a small ceremony when we are closer to completion and can finalize a date. Once that is accomplished, we will be able to reopen the memorial bricks program for anyone else who wishes to contribute!

Concept Plan for Park


Bridgeville Self Storage Expansion

Where: S. Main Street, between Elm Street and the Bridgeville Laundromat/Thrift Store/ Tony’s Pizza

 

What: Expansion of the existing self-storage facility that fronts Rt. 13. This is the same property, just the back end of it. 

Bridgeville Self storage location map

Links: 

Plan Sets: May 20, 2025 Planning and Zoning Meeting Link:https://bridgeville.delaware.gov/events/planning-and-zoning-meeting-32/

https://www.bridgevillestorage.com/

 

 


FDPN Management, LLC – Outside Town Limits

Where: Rt. 13 Southbound – Former site of CJ’s Auto, 20354 Sussex Highway, TM#’s  131-19.00-5.00 and 131-19.00-4.00, approximately 12.70 acres combined

What: Eight 10,000 sq. ft. warehouse-style buildings for flexible workspace units from 2,500 sq. ft., and one 52,000 sq. ft. manufacturing/warehouse distribution center. The proposed project is
similar to Camden Business Center.  The site may be known as the previous location of the “Concrete Crusher” Proposal from 2021 to 2023, which was denied by Sussex County in 2023.  This project replaces that plan. 

aerial fpdn management

Links: 

Plan Sets: April 2, 2024 DelDOT TIIF Study meeting (Begins on Page 23): https://deldot.gov/Business/tiif/pdfs/2024/TIIF%20Council%20Meeting%20Presentation%20Slide%20Deck%204-2-24%20FINAL.pdf

Wastewater Facilities Construction Permit: https://dnrec.delaware.gov/public-notices/wr20250278/

Sussex County Council Meeting for Wastewater Annexation (Page 19): 

https://sussexcountyde.gov/sites/default/files/packets/Full%20Packet_21.pdf

**More information on this project may be obtained by contacting Sussex County. 

 


Mountaire Farms of Delaware, Inc. – Outside Town Limits

Where: Rt. 13 Southbound and Newton Road/404, Just north of O.A. Newton and Lindenmere. TM#’s 530-16.00-12.00 and 530-16.00-11.00, approximately 172.46 acres combined

What: A feed mill and grain storage facility with direct rail access, expected to create around 84-87 jobs (varying numbers referenced across applications). 

Links: 

Sussex County Planning and Zoning Meeting Docket and Documents from February 23, 2023

https://connect.sussexcountyde.gov/PublicDocket/#/details/CZ%202003

Aerial View of Mountaire properties

2025 Sussex County Comp Plan Annual Report – https://sussexcountyde.gov/sites/default/files/PDFs/Sussex_County_Comp_Plan_Annual_Report_2025.pdf

  • Mountaire Farms has purchased 167 acres of land near the intersection of U.S. Route 113 and Route
    404 in Bridgeville, Delaware, for $8.5 million. The site will be home to a state-of-the-art feed mill with
    grain storage and packing facilities. The facility is planned to produce up to 30,000 tons of feed per
    week and will include at least six large silos with a total storage capacity of approximately three million
    bushels.
    A key feature of the project is a rail spur running along the southern edge of the property, capable of
    accommodating up to 100 rail cars to support efficient grain delivery. The project is expected to create
    around 250 construction jobs and approximately 84 permanent positions once operational. While a
    specific construction timeline has not been announced, Mountaire is actively advancing the project
    through engineering, design, and regulatory approval phases. The investment supports the company’s
    broader strategy to expand its feed production capabilities and optimize grain transportation. This is
    an important economic driver in Sussex County and Sussex County Economic Development is doing
    everything to keep this project moving.

FY25-26 CRISI Recipients: Project Summaries – U.S. Department of Transportation – https://railroads.dot.gov/elibrary/fy25-26-crisi-recipients-project-summaries?fbclid=IwY2xjawVFif1leHRuA2FlbQIxMABwZG9mAWJyaWQRMTZPMGh2cG1JR1JrTExldlJzcnRjBmFwcF9pZBAyMjIwMzkxNzg4MjAwODkyAAEeWcZdyz5IHVrnfm5Qr0iYsQy6K42fBJSebuxT4LNDT-vTuqT-7eBw7dpw8W8_aem_epmNYSl2hO2IQibFWQgb1A

us department of transportation snippet for mountaire rail

 

 

 

 

 

 

 

 

 

 

**More information on this project may be obtained by contacting Sussex County.